U.S. HALEU Production by 2022 First-of-a-Kind, NRC-licensed HALEU production capacity under construction in Piketon, Ohio with support from U.S. DOE. Completed assembly of 16 centrifuges. Construction of "balance of plant" systems well underway. āœ“ License application submitted and NRC is conducting its review. Program remains on cost and schedule - however, some COVID- related challenges in the supply chain could have an impact. Centrus Fueling the Future of Nuclear Power Centus expects to begin demonstrating production of HALEU (19.75% U-235) early next year. 4