Minas-Rio Impairment Considerations and Project Delivery slide image

Minas-Rio Impairment Considerations and Project Delivery

CAPEX ESCALATION RECONCILIATION $bn 5.8 1.0 Approved budget FOOS delay 0.8 0.5 0.2 0.3 Impact of licences and agreements 0.6 8.8 8.2 Escalation and price amendments FX net of hedge Capex review items Revised budget Contingency Revised budget incl. contingency 9