Reg Return Assets - Tariff Determination (Baspa II)
Operating and
Maintenance expenditure
O&M expenditure is as per contracts with our providers and is fixed @2.5% p.a. of the Project cost with escalation at annual
intervals based on CPI & WPI annual escalation factor
Depreciation on assets
Interest on Term Loan /
Working Capital Loan
Return on Equity and tax on
Return on Equity
Annual Revenue Requirement
Fixed Charge
Depreciation on assets is available @4.31% currently and will end on FY 25
Interest on permitted debt is also added to the costs to arrive at the Annual Revenue Requirement
16.0% of the equity investment is added to the above costs to arrive at the ARR. Further, this prescribed rate is post tax
Accordingly, the tax on return on equity is also added
Incentive:
Interest on T/L and
depreciation are paid monthly
For each additional 1% of availability beyond normative availability addition RoE of 0.35% is paid with maximum
of 2% of additional RoE
Variable Charge
ROE, Tax, O&M and Interest on
WC is payable on a per unit basis
the minimum design energy
Incentive:
Any Secondary Energy, energy produced in excess of design energy up to 155 MUs is eligible for incentive and is
billed at Rs. 3.15 per kwh
Design energy - Minimum energy threshold required to be produced by plant. If any year Design Energy is not met due to lower flow of water in
the river, the shortfall amount is recovered in the next year.