HERMOSA PROJECT Study work and critical path infrastructure development progressing to plan WTP2 and dewatering well construction Link-Belt Link-Belt 80160 III SOUTH32 Development studies • Taylor feasibility study on-track for completion mid CY23 Clark PFS selection study on-track for completion end CY22 Water • State permits received to complete dewatering program Dewatering is a critical path item to first production which will enable access to both the Taylor and Clark orebodies 6 of the 9 required dewatering wells, ahead of shaft sinking, are expected to be completed in FY23 Construction of the second water treatment plant (WTP2) to support orebody dewatering is underway and expected to be commissioned in Q4 FY23 Tailings storage • We have established the first of two state-of-the-art dry stack tailings storage facilities Power Discussions ongoing to secure 100% renewable energy from local providers SLIDE 40