FY22 Overview & Safety Program Update
HERMOSA PROJECT
Study work and critical path infrastructure development progressing to plan
WTP2 and dewatering well construction
Link-Belt
Link-Belt
80160
III
SOUTH32
Development studies
•
Taylor feasibility study on-track for completion mid CY23
Clark PFS selection study on-track for completion end CY22
Water
•
State permits received to complete dewatering program
Dewatering is a critical path item to first production which will enable access to both
the Taylor and Clark orebodies
6 of the 9 required dewatering wells, ahead of shaft sinking, are expected to be
completed in FY23
Construction of the second water treatment plant (WTP2) to support orebody
dewatering is underway and expected to be commissioned in Q4 FY23
Tailings storage
•
We have established the first of two state-of-the-art dry stack tailings storage facilities
Power
Discussions ongoing to secure 100% renewable energy from local providers