Koç Holding Investor Presentation
2018 Refinery Maintenance Schedule & Capacity Utilization
Even after the 2018 maintenance schedule, we aim to exceed our full total capacity utilization target and
reach 104.6%.
Unit
Plt 7000 Crude Oil Unit
Quarter
Q4'17-Q1' 18
Duration (weeks)
Reason
11-13 in 2018
Revamp
İzmir
Hydrocracker, DHP & Platformer
Q1
5-6
Periodic Maintenance
Plt 4000 FCC
Q2
5-6
Plt 2 Crude Oil & Vacuum Unit
Q4
5-6
Plt 5 Crude Oil & Vacuum Unit
Q2
5-6
İzmit
Plt 25 Crude Oil & Vacuum Unit
Q4
5-6
Periodic Maintenance
Plt 47 Hydrocracker Complex
Plt 63 CCR & DHP
Q2
4-5
Q4
5-6
Kırıkkale
All Units
Q1
6-7
Battery Shutdown
Batman
Plt. 100/Crude Oil & Vacuum
Q1
4-5
Periodic Maintenance
2018 Crude Capacity Utilization
26.8 mn tons (95.4%)
2018 Total Capacity Utilization
29.4 mn tons (104.6%)