2022 State Budget and Fiscal Incentives Presentation
Phasing Out Coal Scenario
120
100
80
Skenario Zero Carbon 2060 (%)
1
7
9
8
29
45
50
53
8
60
40
。。
20
68
62
59
24
11
0
2020
2045
2050
PLTU
2025
2030
2040
PLTGU Nuklir ■ PLTA PLTP EBT Lain PLTS + PLTB
Skenario Zero Carbon 2060 (TWh)
1800
1600
1400
1200
1000
800
600
400
200
0
2020
2025
2030
PLTU
PLTGU
Nuklir
■ PLTA
2040
2045
2050
2060
2060
PLTP
EBT Lain
PLTS + PLTB
In 2060 All Power Plants in Indonesia are Using
Clean Energy
1. The market size utility in 2060 is 1,800 TWh, currently electricity production is 300
TWh plus the launch of 120 TWh from the 35 GW program, so there is room for
1,380 TWh for additional New Renewable Energy (NRE) generating capacity.
2. From 2020 onwards, the portion of PLTU capacity will be reduced (in the graph, it
can be seen from the decreasing black color).
3. Efforts to retire fossil power plants will start in 2030 and significantly decrease in
number by 2040, following the completion of the power plant contract.
4. Nuclear plants will enter in 2040 to maintain system reliability as nuclear
technology becomes more secure.
5. Phase out all coal-fired power plants in 2056, because they have been replaced by
NRE.
6. Meanwhile, the development of NRE power plants will experience a massive
increase starting in 2028 due to the advancement of battery technology which is
getting cheaper. Then it will increase exponentially starting in 2040. And by 2045,
the portion of NRE will already dominate the total power plant. The next decade,
all power plants in Indonesia came from NRE.
Source: Ministry of Finance
111View entire presentation