29 Q1 2022 Results May 2022 ENGIE Nuclear phase out in Belgium Indicative theoretical total (Belgium + France) nuclear production 47.4 TWh 2021 c.44 TWh¹ 2022 c.33 TWh¹ 2023 c.32 TWh¹ 2024 c.23 TWh¹ 2025.... Operated ENGIE End of capacity capacity operations / Nuclear reactors Operator @100% (MW) (MW) contracts Doel 3 ENGIE 1,006 903 1-Oct-2022 Tihange 2 ENGIE 1,008 905 1-Feb-2023 Doel 1 ENGIE 445 445 15-Feb-2025 Doel 4 ENGIE 1,038 932 1-July-2025 Tihange 3 ENGIE 1,038 932 1-Sep-2025 Tihange 1 ENGIE 962 481 1-Oct-2025 Doel 2 ENGIE 445 445 1-Dec-2025 Chooz B (swap) EDF (100) 2025 Chooz B (drawing rights)² EDF 750 2037 Tricastin (drawing rights)³ EDF 468 2031 TOTAL 6,161 1. Belgium + France. Indicative volumes @ ENGIE share assuming a theoretical 85% availability 2. Chooz: 750 MW * average availability of total EDF nuclear fleet in France (excl. Tricastin) 3. Tricastin: 468 MW * local availability of Tricastin units c.9 TWh¹ 2026