Anglo American Minas-Rio Project Update slide image

Anglo American Minas-Rio Project Update

SHIPPED FIRST ORE ON 25 OCTOBER 2014 FOOS delivered safely and responsibly within revised plan and budget • First Ore on Ship two months ahead of schedule • • • Capital saving 0.4 billion $8.4 billion. Ramp-up: 18 20 months post First Ore on Ship 13 shipments to customers in China, India, Middle East and Europe (by end March) Production of 1.2 million tonnes (Q1 2015) • The team is well positioned to deliver ramp-up, safely, by Q2 2016 • ~4,000 employees (steady state) • • Diversified team with several years of mining experience Production guidance: 2015: 11-14 million tones 2016: 24-26 million tones * All tones on wet basis H 6
View entire presentation