Investor Presentaiton
Raipur Energen Limited
Asset Details
Capacity (MW)
Acquired from
Technology
Location State
Status
COD
PPA
Equipment
Fuel Supply Agreement
Evacuation
Arrangement
Water
-
1,370 MW (2 units of 685 MW each)
GMR Group in Aug 2019
Supercritical
Raikheda, Raipur district, Chhattisgarh
Operational
Unit 1 1st June 2015
Unit 2 1st April 2016
Short term PPA with GUVNL to supply
1,000 MW power at INR 3.16/kWh under
Case-4 norms
Current PPA tenure till Dec 2019
Super critical BTG equipment supplied by
Doosan Heavy Industries (South Korea)
Coal for GUVNL PPA available under
Case-4 from Korea Rewa and Korba Coal
fields of SECL
E-auction coal from MCL - IB Valley and
SECL Raigarh coalfields based on
proximity to the plant
BPTA signed with PGCIL for evacuation
of 816 MW (WR - 386 MW & NR - 430
MW) at Raipur substation through
dedicated transmission line (65 km)
Water allocation for 36 MCM approved by
Government of Chhattisgarh
Plant Location
Plant location:
Raikheda
village,
district, Chhattisgarh
Raipur
adani