Building the Large-Scale Gross Mine
Solid Performance and Strong 2018 Outlook
Company Highlights:
-
In the past five years Nordgold successfully built two
large scale and highly efficient mines the Bissa and
Bouly mines in Burkina Faso - investing approximately
US$390m
Gross project is the next on the pipeline. The mine to be
launched in Q3 2018
Public debate for the Montagne d'Or project was held in
French Guiana. Nordgold will consider adjustments to the
Environmental and Social Impact Assessment reports
and then subsequently apply for construction and mining
authorisations
Target Positive Free Cash Flow Generation at All Mines
1200
200
Organic production growth based on existing projects
pipeline, which allows disciplined M&A approach
Gold Production (koz)
985
950
968
900
1000
869
800
600
400
2014
2015
2016
2017
2018 F
2018 Outlook:
Gold production is expected to be in the range of 900 - 950 koz
The growth will largely be driven by the contribution of commencing of underground operations at the Berezitovy which
create access to the high grade ore, and the launch of the Gross mine
AISC guidance of US$975/oz - US$1,025/oz
Capex is anticipated to be approximately US$500 million
3
nordgold
more than goldView entire presentation