Investor Presentation: Q3 & 9MFY2024

Update on Expansion LIQUIDS DIVISION 1. Kandla Port - 35,000 KL Capacity expected to commission in Q4FY24 2. JNPT Port - 110,000 KL Capacity expected to commission in phases and will fully commission by June 2024 4. Mangalore Port -76,000 KL expected to be partially operational by the end of FY24 and the balance in Q1FY25 Kochi Port - Acquired 16,000 KL Liquid Storage Terminal in FY24 and commissioned 20,000 KL in Q3FY24 5. Haldia Port -50,000 KL Capacity Completed 6. Post Expansion, Liquid Storage Capacity will reach ~1.90 million KL GAS DIVISION 1. Two major cryogenic LPG projects at Pipavav and Mangalore of 45,000 metric tons and 85,000 metric tons respectively are progressing well INVESTOR PRESENTATION: Q3 & 9MFY2024 AEG AEGIS AEGIS 9