Investor Presentaiton
ANNUAL REPORT
P
Private Power and Infrastructure Board
ANNUAL REPORT
Private Power and Infrastructure Board
Key Highlights of the Year
As one-window facilitator on behalf of the Government of Pakistan, PPIB is responsible to promote,
encourage, facilitate and safeguard private investment in power sector as mandated through "Private
Power and Infrastructure Board Act, 2012".
The Financial Year 2019-20 was a challenging year for PPIB in terms of continuing office operations and
providing round the clock facilitation to IPPs during COVID-19 outbreak. Despite various hurdles and
hardships created during the pandemic, PPIB handled the situation smartly and while adopting
necessary precautionary measures as envisaged under Corona SOPs continued working smoothly.
Online meetings were held with project sponsors whenever required, at PPIB premises after strictly
adhering to the safety SOPs. Meetings to evaluate the performance and progress of IPPs was also a
regular practice. By virtue of achieving critical milestones by various IPPS under PPIB's expert
facilitation, the year 2019-20 brought many success stories for the power sector of Pakistan which will
be discussed in forthcoming lines. The Pandemic jolted the economic and social activities world-wide
including Pakistan. Due to same reasons, various projects' timelines were slightly affected, however,
due to smart and proactive approach adopted by PPIB as well as active participation of projects'
sponsors prevented the severity of the Pandemic.
Over the recent years, private investments in mega thermal projects (including Thar coal, imported coal
and RLNG), Renewable Energy projects (Hydro, Wind and Solar) and HVDC transmission line have
played decisive role in expansion and diversification of country's power sector. During the year, PPIB
expedited portfolio of projects consisting of hydropower, Thar coal, imported coal and RLNG, and as a
result, various IPPS were able to find headway towards accomplishment of critical milestones which
broadly include issuance of LOS/TLOS, execution of project agreements, achievement of Financial
Closures, tariff and land acquisition processes etc. Fuels wise detail of IPPs being processed by PPIB
during 2019-20 is illustrated as follows:
Hydropower
Thar coal
Imported Coal
RLNG
PPIB is committed to reshape the current fuel mix
and to make it largely dominated by prioritized
indigenous and renewable fuels. In this regard, PPIB
has already started delivering success stories and has
so far materialized three hydro and one Thar coal
based IPP of 993 MW cumulative power generation
capacity. Similarly, less expensive RLNG and imported
coal based power plants are also under active
processing, however, owing to government priorities
and policies, such fuels are no more in the priority list
of GoP/PPIB for achieving the ultimate goal of
optimizing indigenous and renewable resources in
country's fuel mix basket.
<<
Promoting indigenous coal and hydro
resources for power generation
Another 2 hydro IPPS of 1604 MW at
advance stages of construction
Another 2 Thar coal based IPPs are under
construction after achieving Financial Close
while several other IPPS started
construction work before achieving
Financial Close
Pakistan's first private sector Matiari-Lahore
HVDC Transmission Line Project being
facilitated by PPIB is at final stages of
construction.
»
3 IPPs of 2082 MW commissioned through PPIB
during 2019-20
Pakistan's first Thar coal based IPP
commissioned during 2019-20
Overall 40 IPPs of 17,551 MW commissioned by
PPIB which constitutes approx. 50% of total
installed generation capacity of country.
Playing lead role in implementing CPEC based
power generation projects which include 13
projects of 11,648 MW and one Transmission
Line project
affordable and sustainable Power additions by
PPIB.
2020 was a challenging year for PPIB as a number of
IPPs were approaching towards advance to final stages,
hence in such a critical stage, all such IPPs were
required maximum facilitation from PPIB. As a result of
PPIB's relentless efforts, three IPPS, (1,320 MW imported
coal based IPP at Hub, 660 MW Thar coal based IPP at
Thar Block-II and 102 MW Gulpur Hydro IPP)
successfully achieved Commercial Operation Date
(COD) and are currently feeding electricity to the
national grid. In addition to power generation projects,
PPIB is handling a mega and state of the art
Transmission Line Project which is not only the first
private sector project of country but also the first project
which is equipped with HVDC technology which is
highly efficient technology in transmitting power at longer destinations. The project started
construction activities in December 2018 and in a short period of time, inspite of the COVID-19
pandemic challenge, completed more than 85% of the construction work till June 2020.
Highlights of major laurels achieved by PPIB during 2019-20 in terms of processing power generation
and transmission line projects are described hereunder:
14110
MW
No.
MW
No.
MW
No.
MW
No.
MW
15
6277*
07
4950 *
02
1620
01
1263
11
*Including Gulpur, Engro and CPHGC projects which achieved CODs during 2019-20
12View entire presentation