FY22 Overview & Safety Program Update
CAPITAL PROJECTS PIPELINE
We have a pipeline of projects phased from pre-feasibility through to execution
Operation
Safe and reliable capital
Illawarra Metallurgical Coal
Project
Transition to Appin single longwall
Improvement and life extension capital
Worsley Alumina
Worsley Alumina
Worsley Alumina
Brazil Alumina
Brazil Alumina
Hillside Aluminium
Sierra Gorda
Sierra Gorda
Cerro Matoso
Australia Manganese
South Africa Manganese
Growth capital
Hermosa
New mining areas
Mud-washing
Coal to gas conversion
De-bottlenecking Phase 2
MRN life extension
AP3XLE
De-bottlenecking
Fourth line expansion
OSMOC project
Eastern Leases
Rail infrastructure
Taylor Deposit
Hermosa
Ambler Metals
Notes:
a.
PFS
FS
Clark Deposit
Arctic Deposit
Execution
FY23
Productivity and
improvement
Life extension
FY24
Decarbonisation
Project milestones are conditional on regulatory and internal investment approvals, and are subject to change. FS means feasibility study. PFS means pre-feasibility study.
FY25
Commentary
III
SOUTH32
Appin single longwall to deliver efficiencies from FY25
Subject to regulatory approval
FS expected in FY23
FS for first boiler conversion expected in FY23
~4% expected increase in plant capacity from H1 FY26
PFS expected in late CY22
Implemented with pot relining over FY23-FY28
~6% expected increase in plant capacity from Q2 FY23
FS expected in mid CY23
In execution, may trigger mine contract extension 36
FS expected in Q2 FY23
FS expected in FY23
FS expected in mid CY23
PFS selection study expected in late CY22
Arctic PFS underway by the Joint Venture
SLIDE 25View entire presentation