ISA CTEEP Investment and Infrastructure Update
CORPORATE
ISA CTEEP and its subsidiaries Assured
STRUCTURE Annual Revenue (RAP)
Annual Revenue (RAP) 2018/2019 Cycle
BRL 3.4 billion
Operation Status1
Location
RAP Cycle
2018/20191
(BRL million)
ISA CTEEP
IE Madeira
ERB 1
Operational
Operational
São Paulo
2,421
Rondônia / SP
497
RAP ISA CTEEP
Cycle 2018/2019
(BRL million)
2,421
253
Share (%)
ISA CTEEP 100%
Consolidation
Fully consolidated
IE Paraguaçu
IE Garanhuns
Under construction
Under construction
Paraná
267
134
ISA CTEEP 51% / Furnas 24,5% / Chesf 24,5%
ISA CTEEP 50% / TAESA 50%
Equity method
Equity method
Bahia / MG
107
53
ISA CTEEP 50% / TAESA 50%
Equity method
Operational
Pernambuco
87
44
ISA CTEEP 51% / Chesf 49%
Equity method
IE Aimorés
Under construction
Minas Gerais
71
36
ISA CTEEP 50% / TAESA 50%
IE Pinheiros
IE Serra do Japi
Operational
Operational
São Paulo
54
54
ISA CTEEP 100%
São Paulo
60
60
ISA CTEEP 100%
Equity method
Fully consolidated
Fully consolidated
IE Aguapeí
IE Itaúnas
IE Itaquerê
IENNE
Lot 13
Under construction
Under construction
Under construction
São Paulo
54
54
ISA CTEEP 100%
Fully consolidated
Espírito Santo
47
47
ISA CTEEP 100%
Fully consolidated
São Paulo
46
46
ISA CTEEP 100%
Fully consolidated
Operational
Tocantins
44
44
ISA CTEEP 100%
Fully consolidated
Under construction
Santa Catarina
38
38
ISA CTEEP 100%
Fully consolidated
IE Tibagi
Under construction
SP / Paraná
18
18
ISA CTEEP 100%
Fully consolidated
IE Sul²
IEMG
Evrecy
Operational
Operational
Operational
Rio Grande do Sul
18
9
ISA CTEEP 100%²
Minas Gerais
18
18
ISA CTEEP 100%
Equity method²
Fully consolidated
Espírito Santo
7
7
ISA CTEEP 100%
Fully consolidated
IE Itapura
Lot 103
Under construction
São Paulo
11
11
ISA CTEEP 100%
Fully consolidated
Under construction
São Paulo
Total
10
3,876
10
ISA CTEEP 100%
Fully consolidated
3,358
Notes: 1 RAP considers 100% of the project value. For projects under construction RAP of the bid | 2 Celebration of Purchase Agreement to acquire 50% of Share Capital in April/2018. The closing of the deal is subject to