Investor Presentaiton slide image

Investor Presentaiton

Project Caymus Darwin a • Project 31% complete Recruitment of all personnel on track with current onsite workforce circa 120 Bulk earth works and civil ring beams for 11 tank complete Minimal disruption from the first wet season All 11 tanks under construction All major subcontracts for the tank package have been awarded • Safety performance is good with 18,000 hrs LTI free Design of balance of plant underway Balance of plant procurement underway Project has GREEN traffic light designation 8