Northland Power Capitalized Growth & Strategic Overview
Hai Long
Progressing to financial close
1.0GW
Hai Long comprises two adjacent sites: 532 MW Hai Long 2 and 512 MW Hai Long 3
Localization plan obtained in 2021
Tendering for main components concluded, preferred supplier agreements signed
EIA amendment approved, allowing for 14MW turbines
Main design works (turbine foundations, Offshore and onshore substations) and
corresponding certification progressing well and on track, now well into the detailed
design phase
Launched project finance activities
Commenced with sell-down process
Timeline For Hai Long Development
2021
2022
Project optimization
through offtake, design
and procurement
Achieve Financial
Close
2023
2026-2027
0
NORTHLAND
POWER
HL
3
HL
2
Taipei
City
Taiwan
Construction
underway
Expected
Commercial
Operations