Financial Overview H1 2020

Reftinskaya GRES: handover completed ahead of schedule RGRES on Financial result of Enel Russia 2 bn RUB 20 June 2019 ! 08 August 2019 Signing Conditions precedent satisfaction: ER's EGSM approval FAS approval 14.7 bn RUB RGRES off ER's balance sheet 01 October 2019 Inventory Title transfer Completion T enel RGRES on Financial result of the Purchaser 4 bn RUB + Purchase of several categories of stocks (c.2bn RUB) 01 July 2020 Up to 3 bn RUB End of Transition Period • ER operated RGRES under the lease, title; personnel maintained by ER The Purchaser applied for permits & licenses 9 months 5 years Earn-out (contingent component) to Annual payments up 600mn RUB each if actual net output and/or DAM price exceed the reference values 9