ADB-PLN Electrical Grid Strengthening Program
Java-Bali 500 kV Power Transmission Crossing
Financing
Project Cost: $249 million)
$20.84 million ADB (including $2.08 million co-financing
from AIF), plus parallel co-financing from KfW
Approval: 3 Dec 2013
Transmission of power from East Java to Bali at 500 kV optimal
solution to improve the power supply in Bali based on least-cost
power system studies.
Coupling Bali with more efficient generation capacity in Java,
transmitting power from Java would be a more technically and
economically feasible option before installing new generation
plants in Bali given demand growth in Bali.
•
•
SCOPE
Extension/upgrading of 11 existing SS
New 500/150 kV SS - cancelled
• 500 kV TL crossing the Bali Strait (KfW and PLN) with a
total transmission capacity of 3,600 megavolt-amperes
(MVA) with power capacity of 3,000 MW - cancelled
yeman
Kraksaan
Probolinggo
Component 1.
Paiton 500 kV SS
extension (ADB)
Lumajang
Tempeh
Kunir
Date 23rd Feb 2021
Nusa Barung
Paiton
Besuki
Situbondo
Component 2.
500kV Paiton to
Watudodol TL, 131
km (ADB)
Leung
Component 3. 500 kV
OHL Bali Strait crossing,
4km (KfW)
Gn. Raung
Jember
Genteng
Watudodol Segara Rupek
Kalipuro
Banyuwangi
Component 4. 500 kV Segara
Rupek to Gilimanuk TL, 10km
(PLN)
Gilimanuk
Negara
Taman
Nasional
Meru Betiri
Kesilir Gradjagan
SINGARAJA
Component 5. 500kV
Gilimanuk to New
Kapal TL, 75 km (ADB)
Pulu
Antosari
Component 6. Antosari
500/150 kV new SS (ADB)
BALI