Investor Presentaiton
Growth by site
CDC has successfully grown its portfolio of assets and has a range of diversified growth options that now
include the expansion into New Zealand
cat
DATA CENTRES
Facility
Capacity Capacity
(MW) contracted¹
Phase 1:
Build
Phase 2:
Fit-out phase
Hume 1
6MW
>95%
Completed
Completed
1111
Hume 2
6MW
100%
Completed
Completed
Hume 3
9MW
>95%
Completed
Completed
Hume 4
25MW
70%
Completed
In progress
Hume 5
20MW
In progress
Hume Additional
120MW+
Future build
Fyshwick 1
18MW
Eastern Creek Site Plan
Fyshwick 2
21MW
>95%
80%
Completed
Completed
Fyshwick Campus 2
50MW+
Future build
Eastern Creek 1
7MW
>85%
Completed
Eastern Creek 2
13MW
100%
Completed
FY22 onwards
Future build
Completed
In progress
Future build
Completed
Completed
Eastern Creek 3
28MW
>55%
Completed
In progress
Eastern Creek 4
37MW
Eastern Creek 5 & 6
50MW
Hobsonville (NZ)
10MW
80%
Silverdale (NZ)
10MW
80%
1
FY22 onwards
Future build
FY22 onwards
FY22 onwards
contracted capacity includes reserved and first right of refusal capacity and based on space capacity
In progress
Future build
In progress
In progress
Silverdale Artist Impression
14
14View entire presentation