Workforce in ABWR Construction
·
Owner's Project Management Team in case of Kashiwazaki-Kariwa 6&7
civil engineering architectural engineering Omechanical & electric engineering Pre-operation
(man year)
250
Start of project
Construction permit issued
200
150
100
50
Total:about 1300men
from the start of project
1
2
3
Unit 1 Turn over
Unit 2 Turn over
5
6
7
8
year
OECD
Note: For twin ABWR plant: about 1,300 men-year, out of which: mechanical &
electrical (average57, max 72); architect (19, 22); civil (20, 24); administration (61, 82)
Other resources utilized in Kashiwazaki-Kariwa 6&7
-
-
(Source IAEA-TECDOC-1390.)
Manpower-construction [ man-hours]: U6 14,400,000; U7: 10,800,000
Materials Piping [tons]: U6: 11,000.; U7: 6,000.
Concrete [m3]: U6: 200,000.; U7: 167,000.
OECD NEA Workshop on Project and Logistics Management, Paris, 11th March 2014 16View entire presentation