Vale's Performance in 3Q22
Vale's Performance in 3Q22: Iron Ore
We are progressing on assets debottleneck
Serra Norte
S11D
Gelado project: start-up phase 1 expected in 4Q22 and ramp-up in 2023
NB: previous license granted, and start-up expected in 2024
Applying for rolling licenses to sustain production level
New crushers, mobile plants and +10 Mtpy project (start-up in 4Q22) supporting production
increase in 2023, but still limited by jaspilite restrictions
▲ Jaspilite restrictions: waste crusher required to process large compact blocks
Itabira
Itabiruçu dam: first phase raising works concluded in 3Q22 and second phase in 2Q23
▲ Licensing and development of tailings/waste stockpiles areas
Brucutu
A Torto dam: works completed, pending licensing to start-up
▲ Licensing and development of tailings/waste stockpiles areas