UltraTech's expansion plan (Phase-II) Total Cement capacity of 22.6 Mtpa at a capex of Rs 12,886 Crs ($76/t) and IRR >15% North Unit Project Capacity Rajpura, Punjab GU G 2.6 Kotputli, Rajasthan IU B 1.8 Total 4.4 ADITYA BIRLA UltraTech Central Unit Project Capacity Maihar, Madhya Pradesh IU B 4.5 East UP, Uttar Pradesh BT G 1.8 Roorkee, Uttarakhand GU B 1.0 West UP, Uttar Pradesh GU B 1.8 Total excl BT 7.3 South Unit Project Capacity East Unit Project Capacity APCW, Andhra Pradesh IU B 1.8 Karur, Tamil Nadu GU G 2.7 Kukurdih, Chhatishgarh Ramgarh, Jharkhand IU G 2.7 GU G 2.5 Arakkonam, Tamil Nadu GU B 1.2 Total 5.2 Bangalore, Karnataka BT B 1.0 Total excl BT 5.7 Capacity mentioned in million tons per annum GU-Grinding Unit, IU - Integrated Unit, BT - Bulk Terminal (not additional capacity), G - Greenfield Expansion, B - Brownfield Expansion 28