Q3 FY24 Distribution Update
Q3 FY24 Industry Update
Power Demand and Supply Trend
Average quarterly peak power demand registered at 213.5 GW for Q3 FY24
177.1
+ 9.5%
IndiGrid
194.0
+10.1%
213.5
Peak power demand witnessed a YoY increase of 10%, however the QoQ consumption
came off by 7%
India has envisioned aggressive generation growth to meet growing consumption demand
☐ Installed capacity at 428.3 GW in Dec'23 vs 410.3 GW in Dec'22
Q3FY22 Q3FY23
Peak Power Demand (GW)
Q3FY24
Key Developments in Transmission / Solar / InvITs
☐ Transmission sector investment:
NIP estimated a capex of ~INR 3,040 billion for the power transmission segment between 2020 and 2025
Based on the upcoming and under construction ISTS, a total investment of ~INR 2,215 billion is expected in the power transmission
segment.
□ MoP has released the National Framework on ESS* to encourage adoption and create ecosystem for development of ESS
-
ESS requirement as envisaged by National Electricity Plan - 2023 by the year 2031-32 is 74 GW (BESS-47 GW & PHP - 27) with
storage capacity of ~400 GWh
2
Estimated fund requirement for above ESS requirement till 2031-32 is estimated at 4,800 billion
Union Cabinet approved VGF# of 3.7 billion for development of 4 GWh of BESS by 2030-31; BESS developers for VGF grant to be
selected through transparent competitive bidding process
Source: 1) CEA Website (2) CEA monthly reports (3) Ministry of Power releases * Energy Storage Systems; #-Viability Gap Funding +Net Distributable Cash Flow