Nikola Investor Day Presentation Deck
90
PAGE
VTOMIN
COOLIDGE CAPEX OVERVIEW
ILLUSTRATIVE PURPOSES ONLY; SUBJECT TO CHANGE
A
B
NIKOLA HQ
(Phoenix, AZ)
~50 miles
MANUFACTURING
FACILITY
(Coolidge, AZ)
EST. CAPEX
PHASE CAPEX
BUILDING
EQUIPMENT
A
PAINT & WELD B
SPEND THRU
DEC'21
Equipment includes truck capacity expansion and fuel cell
power module (FCPM) assembly
Inclusion of paint and weld facilities and equipment
subject to final make vs. buy decision (decision by Q2
2022)
-$105M
~$85M
~$20M
$0
D
Includes Phase 2.0 facility and capacity expansion, commence
buildout of FCPM assembly line, & test track facilities
2022
~$150M
~$70M
~$80M
$0
2023
-$345M
~$95M
C
~$100M C
~$150M
TOTAL SPEND
~$600M
~$250M
~$200M
~$150M
D
Includes buildout of phase 3.0 building and equipment capacity plus
the ramp up of FCPM assembly capabilities
To reduce overall CAPEX Nikola may consider entering into a sale-
leaseback agreement upon plant completionView entire presentation