EGCO Group Sustainability and Portfolio
2
GROW AND SEEK FOR OPPORTUNITIES IN RELATED BUSINESSES
Thai Pipeline Network (TPN) is on schedule with COD in Q4/2022
Thai Pipeline Network (TPN)
EGCO Rayong Industrial Estate
66-T-21010
66-T-2101B
66-T-2201B
66-T-2201A
66-T-2101 A
66-1-2301A
8
YEARS
35EGCO
GROUP
Project Progress: September 2022
99.96%
Project Description:
Type
Oil Transportation Service Business
Location
ā
Saraburi Khon Kaen
Operation Date
Capacity
Contract
Agreement
Q4/2022
5,443 million liters
20 years exclusive rights to operate oil pipeline transportation system with
Thappline (can be extended 10 years x 2 times)
Project Progress:
AEC submitted construction drawings to IEAT for approval on July 8. The reply from IEAT is
expected within July 2022.
Request to the cadastral survey was submitted to Land Office of Rayong province.
EGCO and AEC agreed to terminate the consultancy service agreement effect from October 2022
Smart, Green and Sustainable Industrial Estate to support the investment in EEC
The site of Rayong power plant in Rayong
2023
Area: 621 rai
Business terms: Leasing in long term & selling land plots
Customers: Hi-tech, Innovation, R&D factories
Volume
Unit: Liter
1,410*
+30.6%
Estimated
CAGR
2022
2023
2024
2025
2026
Shareholders:
BIGGAS
55.4%
Note: *2022 volume is based on June - December
EGCO
44.6%
Shareholders:
O
EGCO
100%
16View entire presentation