INFRASTRUCTURE FOR THE FUTURE
TRANSMISSION INVESTMENT IS A PREREQUISITE
Substantial and sequential investment in the transmission network is required to deliver energy security and reliability, support
proposed generation connections, unlock renewable energy resources and reduce total system costs to customers
AEMO
Far North QLD
REZ
Forsyth
Indicative timing 2020
2021-22
NSW
2020
Integrated
System Plan
July 2020
For the National Electricity Market
SA System Strength
Remediation
Mid North SA
REZ
Longreach
Town de
QNI
Proserpine
Mackay
Medium & Large
Central-West Orana
REZ Transmission
Link
Classification Project
SA System Strength Remediation
88
Committed
QNI Minor
2021-22
Gladstone Grid
Reinforcement
Western Victoria Transmission
Network Project
2025-26
VNI Minor
2022-23
Bockhampton
adtone
Project EnergyConnect
2024-25
Bundaberg
Central to
Southern QLD
HumeLink
2025-26
Central-West Orana REZ
Mid-2020s
Transmission Link
Actionable¹
● Brisbane
VNI West²
2027-28
QNI
Minor
Armidale
New England
REZ
Dubbo
Newcastle
Reinforcing
Sydney Sydney,
Newcastle &
Wollongong
Supply
Wollongong
Canberra Hume Link
Preparatory
Activities
VNI Minor
Melbourne
Network investments
expected to deliver $11
billion in net benefits to
the National Electricity
Market (NEM)
Port Lincoln
Adelaide
Project
EnergyConnect
VNI West
South East SA
REZ
More than $19bn (1) of Network
Investment required by 2040
Mount Gadder
• Around $13bn (1) associated with
NSW and TransGrid opportunities
(1) AEMO's Modelled Cost of Projects 2020 ISP
Spark Infrastructure I Investor Presentation | August 2020
Western Victoria
Transmission
Network Project
Queenstown
Launceston
Hobart
Marinus Link
Marinus Link²
- Cable 1
-Cable 2
QNI Medium & Large
2028-29 to 2031-32
2031-32 to 2035-36
2030s
Early-2030s
2026-27 to 2032-33
Required
Central to Southern QLD
Reinforcing Sydney, Newcastle
and Wollongong Supply
Gladstone Grid Reinforcement
New England REZ Network
Expansion³
2030s
2030s
North West NSW Network
Expansion
2030s
Far North QLD REZ
2030s
South East SA REZ
2030s
Future ISP
Projects
Mid North SA REZ
2030s
1 Estimate practical completion including any subsequent testing projects may be delivered earlier
2 Decision rules may affect timing
3 May be accelerated by government initiatives
4 Not shown on map. AEMO requires that preliminary engineering designs be completed by 30 June 2021
2040
•
DEPARTMENT OF PLANNING, INDUSTRY & ENVIRONMENT
NSW Electricity Strategy
Our plan for a reliable, affordable and sustainable electricity system
energy.nsw.gov.au
Drives $8bn of private
investment
Creates > 1,200 jobs
Reduces electricity
bills by $40 per year
NSW Government will seek
to legislate the requirement
for ISP priority projects to
proceed
Projects can proceed ahead
of RIT-T
NSW Electricity Strategy
includes a pilot 3 GW REZ