Investor Presentaiton
Project Management & Assurance Group (PMAG) - End to End Project Integration
adani
Power
Bidding, Site Scouting
Concept
Project Development & Basic Engineering
Integrated Project Management
Execution
Operations
Commissioning
Strength: Team of 90 professionals having hands-on experience of 2,000+ man-years of complete project management cycle of small, medium & large projects
Strong Project Controls
Collaborating & Convergence
Effective Project Delivery
One of India's largest single location thermal power plants
First super-critical power plant : Mundra, Gujarat
Cumulative Capacity: 4,620 MW (330 MW * 4 units + 660 MW * 5 units)
Best in class project execution
。 Synchronization of first supercritical generating unit
within 36 months from inception
。 Plant spread over an optimized layout of 734 acres
。 Industry benchmark in commissioning i.e. 3 units in
single financial year, balance units in the next year
World class logistics management
。 High-speed conveyor belt conveys the coal from
Mundra port to plant 8 km away @ 6,000 mt / hour
。 Sea Water utilised for water requirement of plant
Landmark feat in project execution & transnational supply
India's first commissioned transnational project: Godda, Jharkhand
Ultra-supercritical plants of 1,600 MW (800 MW x 2) commissioned in April & July 2023
Transnational plant to supply electricity from
Jharkhand to Bangladesh
Secure revenue and profitability streams
○
25-year PPA of 1,496 MW (net) with Bangladesh
Power Devt Board
Connected to Bangladesh Grid with a 400kV
dedicated transmission line
О Efficient recovery of fixed & variable costs under
USD-denominated tariff
Commissioned in just 3.5 years from financial
closure despite pandemic lockdown challenges in
India, China, and Bangladesh
18View entire presentation