I-6. Contract Backlogs
Significant contribution to sales in fiscal year ending March 2018
from all-time-high projects carried forward
1,373
437
S
COMSYS.HD
(Unit: ¥100 million)
Social System-Related and Other
• Increase in private-sector,
demand-related civil engineering
projects
• Decline in completed projects
due to delays in orders received
for solar construction projects
931
Social
System-Related
and Other
IT
NCC
NTT
1,013
981
898
March 2014
Beginning of Term
March 2015
Beginning of Term
March 2016
Beginning of Term
March 2017
Beginning of Term
+157
+2
--------
+190
136
550
749◄
NTT-Access
• Increase in cable tunnel repair
projects
• Increase in maintenance projects
◇NTT-Mobile
• Increase in LTE-A negotiations
and construction processes
• Increase due to delays in project
progress
March 2017
End of Term
*All-time-high projects carried forward was ¥101.3 billion recorded
at the beginning of fiscal year ended March 31, 2017.