JSW Neo - Kutehr Hydro Power Plant - 240 MW • Barrage & Intake Barrage concreting completed 86% • Erection of spillway radial gate in Tunneling & Concreting ■ Completed tunneling work ~100% Completed HRT lining ~25% advanced stages JSW Energy Corporate Presentation - Jan 24 Power-House works SW Energy • Power house civil works completed for Unit-1 & Unit-2 • Erection of draft tube liners, spiral casing and stay ring complete in all the three units 59 65