Shaft capacity optimised ● Two deep shafts of ~1,600m each Service shaft: materials & personnel access ● ● Production shaft: ore transfer from production level (~1,600m) to mineral transport level (~360m) • 7.5m diameter - unlocks optionality ● 13Mtpa production capacity Foreshaft sunk, minimising surface impact Sink via SBR technology Service shaft at 550m Production shaft at 340m Anglo American Was Production shaft SBR began sink in January 2023 THE 12