Freyr Results Presentation Deck
Giga America project summary
Targeting 4Q 2023 FID of Phase 1a to maximize IRA incentives and capture surging ESS demand
U.S. development plan summary
●
• Seeking to begin long-lead time orders in 3Q 2023
Targeting Phase 1a FID and start of construction in 4Q 2023
●
Phase 1a:
• Initial 2.5 GWh cell to DC block production capacity
Phase 1b:
• Quickly follow 1a with a larger cell plant and an upgrade to the
2-line plant for a total of ~38 GWh capacity in 2026
Giga America Phase 1a
Nameplate Capacity
2.5 GWh
Giga America Phase 1b
Nameplate Capacity
38 GWh
Subsequent phases are expected in include highly value accretive
upstream and additional downstream expansion, including
cathode active material production
FREYR
Value of fast-tracked U.S. development
Fastest path to giga scale production and participation in IRA
incentives
Focused on developing financing through pull-forward monetization of
IRA PTCs with project level equity from strategic and/or financial
sponsors
Potential to circumvent lengthy project financing process in Phase 1a
Provides flexibility to maximize merchant sales exposure in
undersupplied ESS market
Projected NPVs for Phases 1a and 1b:
Phase 1a: $1.3 billion (1)
Phase 1b: $6.7 billion
IRA Benefit: $3 billion of total projected $8 billion NPV (2)
(1) Includes upgrade and allocated corporate costs and taxes.
(2) Shown as NPV10.
10View entire presentation