Cipher Mining SPAC Presentation Deck
EXPANSION AT EXISTING SITES
Opportunistic expansions at existing sites with available capacity:
Alborz
- Secure a grid connection to import power from the market as
a complement to wind energy
Cipher Mining WHAT'S NEXT?
• Bear/Chief
- Interconnection agreements signed for up to 135 MW per site
- Large load study on going to expand the sites
●
- Increase the data center capacity to match the wind farm
interconnection capacity
NEW SITES & PPAS
Focus on merchant renewable assets exposed to (a) high
technical curtailment levels and/or (b) negative and low market
prices
●
Focus on power plants similar to Odessa
• Continue a live monitoring of other attractive markets (e.g., PJM,
Ontario, SPP)
Alborz Data Center
Bear Data Center
8View entire presentation