Meyer Burger Investor Presentation slide image

Meyer Burger Investor Presentation

Production continuously running, supply chains being further de-risked Modules produced [MWp] 30 2021 FY MEYER BURGER 108 321 . 2022 H1 2022 FY Ongoing production and parallel capacity expansion on track • • • A total of 321 MW was produced in 2022 Ramp-up of the second production line commenced in September 2022 and is expected to require approximately six months to completion Additional production lines (as part of the ongoing 1.4 GW expansion) are expected to eliminate bottlenecks and improve operational performance Supply chain risks are being actively managed in order to maintain continuous production and enable timely ramp-up. Meyer Burger continues to de-risk its supply chain (e.g., first European wafer supply contract signed) 8