Meyer Burger Investor Presentation
Production continuously running, supply chains being
further de-risked
Modules produced [MWp]
30
2021 FY
MEYER BURGER
108
321
.
2022 H1
2022 FY
Ongoing production and parallel capacity expansion on
track
•
•
•
A total of 321 MW was produced in 2022
Ramp-up of the second production line commenced in
September 2022 and is expected to require approximately
six months to completion
Additional production lines (as part of the ongoing 1.4 GW
expansion) are expected to eliminate bottlenecks and
improve operational performance
Supply chain risks are being actively managed in order to
maintain continuous production and enable timely ramp-up.
Meyer Burger continues to de-risk its supply chain (e.g., first
European wafer supply contract signed)
8View entire presentation