NewFortress Energy 2Q23 Results slide image

NewFortress Energy 2Q23 Results

Construction Update FLNG 1 is mechanically complete(15), being installed & expect COD(10) in 60 days(11) FLNG 1 consists of 3 platforms ZN N Platform I Function: Gas treatment Ready September 1st(11) How it works liquefier platforms T Platform II Function: Liquefaction Ready September 10th (11) cryogenic flexible hose system IN AS frood storage vessel ship to ship transfer NEPONERE Platform III UNNAR Function: Power & people Onsite in Altamira LNGC 17 8