Pratt & Whitney GTF Fleet Update
Pratt & Whitney GTF Update
●
●
Background
Rare condition in powder metal driving
accelerated engine removals and inspections
for PW 1100 engine, which powers A320neo
August 2023 initial service instruction and
airworthiness directive issued
Expected fleet guidance to be issued within 60
days for balance of the fleet
Continue to deliver new engines and spare
parts
Other fleets currently expected to be far less
impacted
RTX
●
●
●
●
●
Fleet Management Plan and Impact
Approx. 600- 700 incremental shop visits
from 2023 2026
-
Majority of incremental engine removals will
occur in 2023 and early 2024
Shop visits will primarily be heavy workscope
Approx. 250 to 300-day turnaround time wing-
to-wing
Average of 350 aircraft on ground (AOG) from
2024 2026 with first half of 2024 peak AOG