Pratt & Whitney GTF Fleet Update

Pratt & Whitney GTF Update ● ● Background Rare condition in powder metal driving accelerated engine removals and inspections for PW 1100 engine, which powers A320neo August 2023 initial service instruction and airworthiness directive issued Expected fleet guidance to be issued within 60 days for balance of the fleet Continue to deliver new engines and spare parts Other fleets currently expected to be far less impacted RTX ● ● ● ● ● Fleet Management Plan and Impact Approx. 600- 700 incremental shop visits from 2023 2026 - Majority of incremental engine removals will occur in 2023 and early 2024 Shop visits will primarily be heavy workscope Approx. 250 to 300-day turnaround time wing- to-wing Average of 350 aircraft on ground (AOG) from 2024 2026 with first half of 2024 peak AOG 2