Nikola Investor Day Presentation Deck
39
/
PAGE
VTOMIN
COOLIDGE MANUFACTURING OVERVIEW
FACILITY PROGRESS
JULY 2020
NIKON
Groundbreaking ceremony
NIKOLA HQ
(Phoenix, AZ)
~50 miles\
MANUFACTURING
FACILITY
(Coolidge, AZ)
EST. TIMELINE (1)
PLANT CAPACITY (# of trucks)
PHASE BREAKDOWN
DECEMBER 2020
Install first steel columns
COMPLETED JULY
2021
PHASE 0.5
~1,200
Pilot line, core facilities and
buildings
JULY 2021
1) Estimated; subject to change
2) Inclusion of paint and weld facilities subject to final make vs. buy decision
Core facilities, assembly, and
test road installed
ā Greenfield facility to support BEV and FCEV truck manufacturing
ā Fuel-cell power module assembly expected by 2023 in support of the initial Tre FCEV production
Bosch will provide key components for fuel-cell power module assembly
COMPLETED MARCH
2022
PHASE 1.0
NOVEMBER 2021
~2,400
Main assembly hall
expansions
Assembly expansion area
started
Q1 2023
PHASE 2.0
~20,000
FEBRUARY 2022
Introduction of cab
assembly process line
Assembly expansion area
completed
2024
PHASE 3.0
Milestone
Completed
~45,000
Addition of weld and paint
buildings/infrastructure (2)View entire presentation