Fresnillo Results Presentation Deck
2022 PRELIMINARY RESULTS OPERATIONS
JUANICIPIO (JV WITH MAG SILVER. FRESNILLO: 56%)
-
A
KEY ACTIONS
14
Completed the tie in of the flotation plant to the national grid
Despite the delay, mineralised material from development and initial
production stopes was processed at the Fresnillo and Saucito
beneficiation plants during the year
Development of the mine continued to advance, reaching almost 58km
by the end of the year
Commissioning and tests with low ore grade material are underway
Ramp up of production expected to progress smoothly, with the objective
of achieving nameplate capacity by 3Q23
Once at full capacity, the average silver ore grade is expected to be
around 400 g/t, with the gold ore grade expected to average 1.0 g/tView entire presentation