Nikola Results Presentation Deck slide image

Nikola Results Presentation Deck

0 5 PAGE NIKOLA TREBEV PROGRAM UPDATE 388 KEY UPDATES During Q4, built 30 Pre-Series Tre BEVS off the line in Coolidge ● ● 11 trucks have been completed and commissioned to date o Five (5) trucks were completed and commissioned in Q4 2021 ▪ Two (2) with TTSI, and three (3) in Nikola's test fleet o Six (6) trucks completed and commissioned from 1/1/22 - 2/23/22 Four (4) with dealers, two (2) in Nikola's test fleet 19 trucks are awaiting late part installs (battery packs, e-axles, or displays) or are completing final verification Tre BEV start of production (SOP) scheduled to begin 3/21/22