Vale ESG Presentation Deck slide image

Vale ESG Presentation Deck

Commitment to comply with the GISTM Tailings storage facilities (TSF) operated by Vale will be in conformance with the GISTM: Those with "Extreme" or "Very high" potential consequences, by August 5th, 2023 All other, not in a state of safe closure, by August 5th, 2025 ■ 1st step - Self-Assessment By the 1st Line of Defense Completion by October 2021 A form-based tool for the assessment of each TSF (with supporting evidence). Cover all 77 auditable requirements. 2nd step - Gap Assessment By 2nd Line + external consulting Completion by February 2022 Re-assessment of select TSFs for full compliance Key findings in December 2021 3rd step- External Audit By independent, external party Deadline for completion to be defined Depending on further guidance by the ICMM VALE