14 Vale S.A. Proxy Season 2022 Path to recover production: 2022 guidance drivers Iron ore production Mt 316 2021 320-335 2022E ▪ Improvement of S11D performance with jaspilite crushers and mobile crushers ▪ Higher quality product portfolio Tailings' filtration plants and start-up of Torto dam and raising of Itabiruçu dam (taking capacity to 370 Mtpy) Copper production kt 297 2021 ■ 330-355 2022 ▪ Stable production at North Atlantic mines (Sudbury + Totten ramp up) ▪ Improvement in Salobo mine movement and startup of Salobo 3 Planned maintenance at Sossego Nickel production kt H 168 H 2021 175-190 2022 ▪ Stable production at North Atlantic mines (Sudbury + Totten ramp up) ▪ New projects: VBME and CCM 1 Onça Puma stabilization PTVI furnace rebuild De-risking my VALE