AngloAmerican Investor Day Presentation Deck slide image

AngloAmerican Investor Day Presentation Deck

Met Coal operations set to ramp back up ——--- Anglo American Production • Moranbah back up running; Grosvenor restart prep completed • 2022 guidance 20-22Mt, with focus on safety & stability • 2022 unit costs of ~$80/t High quality product • Premium products: ~85% premium HCC and ~15% PC|16 Moranbah-Grosvenor debottlenecking • Now expected 2025, following 2023 targeted approval • Increases plant capacity by 2.5Mt (saleable, our share) Aquila project • On track for 2022 start - replaces Grasstree ● 7 year mine life¹7 at ~3.5Mt pa 17