Shoals Results Presentation Deck
HIGH REVENUE VISIBILITY DRIVEN BY LONG PROJECT
LEAD TIMES...
14
●
Project Identified
Shoals receives preliminary
design drawings
Project Development
6 months
EPC advances preliminary engineering
and design
Shoals prepares preliminary design, layout,
and pricing
shoals
●
EPC Award
Shoals receives
verbal award
Pre-Construction
3 months
EPC completes
final design
• Shoals completes final
design, layout, and pricing
影
●
© 2022 Shoals Technologies Group
●
Shoals
Purchase Order
Shoals receives binding
purchase order
Pre-EBOS
Construction
3 months
EPC completes pre-EBOS
construction activities
Shoals production
lead time
●
EBOS Delivery
2-3 months
The procurement process typically gives us 12+ months of visibility on demand and many customers
give us long-term forecasts with their needs, further enhancing our visibility
Shoals delivers
system