Nikola Results Presentation Deck
90
PAGE
NIKOLA
Nikola Tre FCEV
Timeline (1)
KEY POINTS
The Nikola Tre FCEV will be developed for two distinct markets (US / EU)
Three distinct build phases (alpha / beta / gamma) with customer deliverable trucks
Each build to be done in both Germany (Ulm) and Arizona (Coolidge) in all phases
US SOP timing planned for June 2023; EU SOP timing planned for Q1, 2024
Product Timeline
STREFCEV
Phoenix, Arizona
Ulm, Germany
1) Anticipated Timeline.
TRUCK UPDATES
Q4 2020
Alpha Design
Finalized
Start Alpha
Builds
2021
Start Alpha
Vehicle
testing
Start Alpha
Builds
Anheuser-Busch
Pilot w/ AB
Road Trials
Start Beta
Builds
2022
Start Beta
Builds
Start Beta Fleet
Trials
Beta Fleet
Customer
ULM FACILITY UPDATE COOLIDGE FACILITY UPDATE Q4 & FY 2020 RESULTS
H2HAUL
Start Gamma
Builds (PHX)
Iveco Project
Funding by EU
FY 2021 OUTLOOK
2023
Start of Production
Tre FCEV North
America
APPENDIX
Q12024
Start of
Production
Tre FCEV EUView entire presentation