NewFortress Energy Results Presentation Deck slide image

NewFortress Energy Results Presentation Deck

First Gas(31) Q4 2020 Development Update La Paz Terminal, Baja California Sur, Mexico NFE's power plant will capture the highest power prices in Mexico(30) Run-Rate Volumes 500-750k gpd 00000 4 Status Update Site Works Construction works have commenced at the terminal Dredging Dredging works on the site have been completed Power We expect to ship three gas turbines to La Paz on Oct. 1st 17