Investor Presentation
2-PIPELINE UPDATE
Projects In Operation, Under Construction & Backlog
1.2 GW in operation and under construction. 811 MWs in final development phase
Country
Project
Туре
MW
B20
Resource
(Hours)
COD
Spain
Los Escuderos
Solar
200
Yes
2,128
4Q21
Chile
Quillagua
Solar
103
Yes
2,950
4Q20
Chile
PMGDS (11 Projects)
Solar
120
Yes
2,109
4Q21-1Q22
Mexico
San Miguel de Allende
Solar
35
Yes
2,300
1Q21
Colombia
Distribution (4 Projects)
Solar
48
Yes
1,957
4Q21-1Q22
Peru
Duna
Wind
18
Yes
4,900
4Q20
Peru
Huambos
Wind
18
Yes
4,900
4Q20
Argentina
Kosten
Wind
24
Yes
5,033
1Q21
Total in Operation
566 (Vs. 541 previous report)
Spain
Belinchón
Solar
150
Yes
2,150
4Q22
Chile
PMGDs (21 Projects)
Solar
189
Yes
2,000-2,700
2Q22-1Q23
Chile
PMGDS (6 Projects)
Solar
57
No
2,000-2,700
1Q22-4Q22
Chile
Teno
Solar
240
Yes
2,186
1Q23
Colombia
Distribution (2 Projects)
Solar
25
Yes
1,990
4Q22
Total Under Construction
661
(Vs. 424 previous report)
Spain
Ayora
Solar
172
Yes
2,212
2Q23
Spain
Tabernas
Solar
300
Yes
2,358
2Q23
Spain
José Cabrera
Solar
50
No
2,156
1Q23
Chile
PMGDS (12Projects)
Solar
105
Yes
2,300
1Q23
Chile
Tamango middle size
Solar
45
Yes
2,200
3Q23
Colombia
Distribution (5 Projects)
Solar
60
Yes
1,900
4Q23-4Q24
Matarani
Solar
80
Yes
2,750
2Q23
Peru
Total Backlog
SOURCE: Company I COD: Commercial Operation Date
811 (Vs. 714 previous report)
Grenergy
renovables