Coolidge, Arizona
Facility Update
Steel Erection Ceremony at Coolidge,
AZ Greenfield Manufacturing Facility.
Coolidge, AZ Manufacturing Facility
Concrete Slab Progress as of February
2021.
TRUCK UPDATES ULM FACILITY UPDATE
Coolidge, AZ Manufacturing Facility
Steel Erection Progress as of February
2021.
Coolidge, AZ Manufacturing Facility
Roofing Installation Progress as of
February 2021.
Coolidge Facility Key Updates
Steel erection began in Coolidge on
December 29, 2020
●
• Roof installation is ongoing
o Siding and concrete to follow
• Manufacturing equipment installation set
to begin May 2021
• Trial production on pace to start in the
summer of 2021