Progressing on portfolio's decarbonization First industrial plant under construction and more to come tra NS04 construction works at Vargem Grande complex Vargem Grande plant under construction Start-up by 2023 with 1.5 Mtpy capacity US$ 125-150 million investment Concentration of 45% Fe ROM Three new plants to be approved 8.5 Mtpy 6 Mtpy 2 Mtpy Oman (approval by 2022) Fazendão (approval by 2023) Fábrica (approval by 2023) Dry concentration ‒‒‒ 17