JUNE AND JULY HAVE BEEN RECORD MONTHS AS NEW CAPACITY RAMPS UP
FINISHED GOODS PRODUCTION VOLUME - YTD
●
July came in significantly better
than June driven by the
Vlissingen expansion and Ogden
ramp-up
Ogden performed much better in
July, with all lines now fully
installed, up more than 250% vs
previous month
Ogden will continue to ramp
up, with full utilization only
expected in 2022
Major success from Vlissingen
operations team, now close to
reaching the monthly target of
20+ million litres and significantly
better than June at +48%
Singapore successfully went live
in July and we received the first
100k litres from co-packing
partner YHS
(Million litres of finished goods)
28.5
JAN'21
28.2
FEB'21
THE ORIGINAL
33.3
MAR'21
●ATLY!
Landskrona
closed for
planned
maintenance
35.5
APR'21
Vlissingen
impacted by
Covid-19
30.9
Ogden not yet at
full capacity but
showing stable
MAY'21
performance
40.1
JUN'21
Start of
production in
Singapore
45.7
JUL'21
Q2'21 EARNINGS PRESENTATION