Freyr Results Presentation Deck
CQP update
Ramp up of process automation and cell production on track with plan communicated at Capital Markets Day
Progress Plan/Key Milestones
First cells assembled and charged: June
25th, 2023
Manual casting and merging
• All else automated
Additional progress following CMD:
Additional PLE commissioning
packages completed
Testing of mechanical processes via
cell production with solvent slurry
Testing program for Nidec underway
Sample production targets: 3Q/4Q 2023
All processes automatic
●
• Improve yields and uptime
• Targeted approval of first samples
Fully integrated production line: 4Q 2023
●
· Target approval of operating parameters
Continuous improvements: 1Q 2024
FREYR
# of CQP cells producedper week
CQP Production Plan: 3Q 2023 - 1Q 2024
Sept Sept Oct
Sample production
Oct Oct Nov
TARGET - # Good cells
Start continuous
casting
Nov
Dec Dec
Increasing
production speed
and quality
Jan
TARGET - # All Cells
Jan
Stabilizing and
validating giga
scale
Feb Feb Mar
Forecasted Line speed
Mar Mar
Production Line Speed (Meters/minute)
5View entire presentation