1st Quarter Investor Update slide image

1st Quarter Investor Update

Capital Expenditure Plan ($ in millions) 2023 2024 2025 2026 4-Year Total Pennsylvania Electric Distribution $300 $300 $300 $325 $1,225 Electric Transmission 550 675 775 650 Pennsylvania Total $850 $975 $1,075 $975 2,650 $3,875 (1) Kentucky Electric Distribution $375 $325 $300 $400 $1,400 Electric Transmission 175 125 100 200 600 Gas Operations 50 50 100 100 300 Generation (non-coal) 50 225 775 800 1,850 Coal-Fired Generation 200 125 100 100 525 Other 100 100 100 100 400 Kentucky Total $950 $950 $1,475 $1,700 $5,075 Rhode Island Electric Distribution Electric Transmission Gas Operations Rhode Island Total Total Utility Capex $250 $275 $300 $225 $1,050 100 225 250 225 800 225 250 325 300 1,100 $575 $750 $875 $750 $2,950 $2,375 $2,675 $3,425 $3,425 $11,900 (1) Includes projected capital expenditures related to replacement generation in Kentucky based upon LG&E's and KU's CPCN filing subject to KPSC approval. ppl 25
View entire presentation